jvanvik
fbae6fc3ed The build standard owns the router model and the line system; one owner per fiber
The routers order reads its model from the build standard (bstd().g, 'keep'
is the old next-model-up rule) and the optical upgrade order its line system
(bstd().sys). The Ops sheet shows "From the build standard: X" with a button
to the sheet. Old saves move a model or line system from an order that was
running into the standard when it has none of its own; a paused order's or
an unhired intern's setting is dropped. opsParam refuses model/sys and points
at bstdSet.

The build standard's order is a generator now: every first job that takes a
fiber dark goes through the optical order's routing test (opsDark, in the
route worker in play), under one shared budget of dark swaps a night (two for
Kevin) and the week-long memory for a failed fiber. A fiber one order worked
on is the other's no more that shift, and decom keeps waves the standard just
upgraded. The plan is checked at every job, since the shift rests between
them: a POP gone or changed by hand meanwhile is skipped. The button still
runs the whole plan at once on the page.
2026-11-07 06:55:01 +01:00
jvanvik
2b48a6ad65 A build standard for the whole network, kept by the intern
One sheet sets the target state for every POP, port and fiber: router
model and count, a second building, a generator, LAG members (split over
both buildings), an exchange port wherever there is one, PNIs spread
over the cities that pay, the line system, the fastest optics that reach
and wave sizes. S.popStd keeps its name; an old {g,rt} standard loads
with the same meaning.

One read-only plan prices every job with the game's own cost helpers,
POPs busiest first, then ports, then fiber hottest first. The sheet's
summary, the MCP quote, "Bring everything up now" and the new "Keep to
the build standard" order all use it, so the quote is what the click
spends. The order works a few jobs a shift through the budget and the
cash floor: a second router before a swap on a busy POP, no generator
under a nogen covenant, no De-Kicks, a line system swap only where the
fiber is quiet or a parallel link carries it, one a shift. New POPs get
the POP part of the standard, and the template's kit no longer pays for
it twice. opsMoNow counts generators and second buildings.